Occupancy certificate and conveyance deed in Gujarat: what the promoter must do and by when

Updated 12 November 2026. Compiled by the Gujarat Estate desk from the sources listed at the end of this page.

Under the RERA Act, 2016, the promoter must obtain the occupancy certificate from the local authority. Where no local law says otherwise, the promoter hands documents and plans to the association within thirty days of it and executes the registered conveyance deed within three months of it. Provisions as in the Act, November 2026.

What happens after the occupancy certificate, in order

StepWhat happensWho or whereWhenSource in the Act
1Promoter obtains the completion or occupancy certificateLocal competent authority (municipal corporation or development authority)Before handoverSection 11(4)(b): the promoter must obtain it as per local laws and make it available to allottees.
2Promoter hands over documents and plans to the associationAssociation of allottees or the competent authorityWithin 30 days of the certificateSection 17(2), where no local law says otherwise.
3Promoter executes the registered conveyance deedSub-Registrar officeWithin 3 months of the certificateSection 17(1) proviso, where no local law says otherwise. The deed includes the undivided proportionate title in common areas.
4Allottee takes physical possessionPromoter and allotteeWithin 2 months of the certificateSection 19(10) puts this duty on the allottee.
5Record the handover dateYour own papersOn handoverThis date starts the five-year defect period in section 14(3).

Periods are from sections 11, 14, 17 and 19 of the Real Estate (Regulation and Development) Act, 2016. Sections 17(1) and 17(2) apply where a local law does not provide otherwise, so ask which rule applies to your project. This is an outline, not legal advice, and it says nothing about any builder.

Download this table (CSV). Last checked 12 November 2026. Free to quote with a link to this page.

What the occupancy certificate is

An occupancy certificate is issued by the local competent authority, which in Gujarat is the municipal corporation or the development authority for the area. It records that the building was completed as per the sanctioned plan and can be occupied. In several Gujarat cities the same permission is commonly called BU permission, short for building use permission. Ask your corporation or the builder which certificate your project holds and what it is called there. Section 11(4)(b) of the RERA Act requires the promoter to obtain the completion certificate or the occupancy certificate, or both as applicable, as per local laws and to make it available to the allottees.

The deadlines in section 17

Section 17 deals with transfer of title. Where no local law provides otherwise, the promoter carries out the conveyance deed in favour of the allottee, together with the undivided proportionate title in the common areas, within three months of the date the occupancy certificate is issued. The promoter also hands over the necessary documents and plans, including common area details, to the association of allottees within thirty days of obtaining the certificate.

Conveyance deed and sale agreement are not the same

The agreement for sale is signed when you book. The conveyance deed is the registered document that transfers the flat and your share in the common areas to you. It is executed at the Sub-Registrar office and carries stamp duty and a registration fee. A buyer who holds only an allotment letter or an agreement has not yet received the deed. Ask for the draft deed early and read it for the flat description and the common area share.

Your own two-month duty

Section 19(10) puts a duty on the allottee as well: to take physical possession within two months of the occupancy certificate. Do not delay the inspection. Walk the flat with a checklist, note defects in writing and take possession with the defects listed, because the five years for defects in section 14(3) start from the date possession is handed over. See RERA defect liability period in Gujarat.

What to ask the promoter before you pay the last instalment

Ask for a copy of the occupancy certificate and check the project name, the building and the date. Ask when the documents will be handed to the association and when the deed will be executed. Ask for the draft deed. If the promoter says the certificate is pending, ask the date it was applied for and the stated completion date on the GujRERA record.

Where the stated dates are recorded

The project page on the GujRERA portal records the promoter, the registration number and the declared completion date. Compare it with the date in your agreement. For the order of checks, see how to check a builder in Gujarat. Our directory lists 1,348 builder and developer listings in four Gujarat cities with Google ratings collected on 30 July 2026. A rating does not show whether a certificate has been issued.

If the deadlines pass

If the promoter does not execute the deed or hand over documents in the stated time, a buyer can complain to the authority under section 31. Keep the agreement, every receipt, the occupancy certificate and a dated record of each request you made.

What this page cannot tell you

This page outlines the RERA Act, 2016. A local law can change the periods, so confirm which rule applies to your project. It is not legal advice and it does not rate any builder.

Questions people ask

Who issues the occupancy certificate in Gujarat?

The local competent authority, such as the municipal corporation or the development authority for the area. In several cities it is commonly called BU permission.

How long does the builder have to execute the conveyance deed?

Under section 17 of the RERA Act, within three months of the occupancy certificate where no local law provides otherwise.

When must documents go to the association?

Within thirty days of obtaining the occupancy certificate where no local law provides otherwise, under section 17(2).

What is the difference between an agreement for sale and a conveyance deed?

The agreement is signed at booking. The registered conveyance deed transfers the flat and the share in common areas to you.

How soon must I take possession?

Section 19(10) says within two months of the occupancy certificate.

Where do I complain if the deed is not executed?

To the authority under section 31 of the Act, through the GujRERA portal.

Read next

Sources

  1. The Real Estate (Regulation and Development) Act, 2016 (Act 16 of 2016), India Code, sections 11, 17, 19 and 31 (listed 13 November 2026)
  2. India Code, section 17 of the Real Estate (Regulation and Development) Act, 2016, transfer of title (listed 13 November 2026, heading and text summary)
  3. GujRERA, Real Estate Regulatory Authority Gujarat portal (opened 13 November 2026)